The Solution
Due to the limited height, the beam of a conventional crane would have been too deep, so Street engineered special cranes to overcome this. In the main production area, six single girder cranes have been configured as two triple girder cranes using rigid link beams. These cranes have a lifting capacity of 9.6 tonnes and each beam features a 3.2 tonne hoist to support the long hose lengths.
Street’s ZX 64 LH – low headroom hoists were also installed and configured so that they would operate without intruding into the space below the beam.
In a second workshop, where heavy-duty and higher diameter hoses of shorter length are produced, a double girder crane of 15 tonnes safe working load has been installed.
In the test and warehousing area a double girder crane of 20 tonnes, with twin 10 tonne hoists, has been installed for cable and drum handling.